Andrew Butt
- Listed as
- architect, pmt consultant/expediter
- Firm
- Interactive Resources
- Based in
- Richmond
- On San Francisco permits
- Mar 2022 to May 2025
10 permits since 2000 (architect on 9 permits, pmt consultant/expediter on 1 permit): 3 completed, 7 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 16, 2025 | Completed final sign-off Aug 2025 | 1050 South Van Ness Av | C B 2 Builders Incorporated | revision to pa #202503061701 revise partition layout sheets a201, a202, a203. reduce number of bedsDetails
revision to pa #202503061701 revise partition layout sheets a201, a202, a203. reduce number of beds | |
| Mar 6, 2025 | Completed final sign-off Aug 2025 | 1050 South Van Ness Av | C B 2 Builders Incorporated | 1st and 2nd floor - interior conversion of existing space into overnight housing quarters with new restrooms and showers. all mep under separate permits. replace one window rm 101.Details
1st and 2nd floor - interior conversion of existing space into overnight housing quarters with new restrooms and showers. all mep under separate permits. replace one window rm 101. | $520,000 |
| Mar 13, 2024 | Completed final sign-off Jun 2024 | 22 Battery St | C B 2 Builders Incorporated | 10/f: revision to permit 202310168720 to replace drinking fountain with accessible bottle filling station due to technical infeasibility and new suspended light fixture.Details
10/f: revision to permit 202310168720 to replace drinking fountain with accessible bottle filling station due to technical infeasibility and new suspended light fixture. | |
| Dec 30, 2022 | Never finaled filed Dec 2022, never issued | 1121 Geary Bl | confirmation that (e) entrances approved and finaled in 1985 in this historic building comply with the sf-abe program. compliance affidavits and plans were submitted in 2018 and 2019 evidencing "technical infeasibility per ordin. 51-16."abe#20190529 -5824/5825/5826/5827/5828.Details
confirmation that (e) entrances approved and finaled in 1985 in this historic building comply with the sf-abe program. compliance affidavits and plans were submitted in 2018 and 2019 evidencing "technical infeasibility per ordin. 51-16."abe#20190529 -5824/5825/5826/5827/5828. | $1,000 | |
| Dec 30, 2022 | Never finaled filed Dec 2022, never issued | 1115 Geary Bl | confirmation that (e) entrances approved and finaled in 1985 in this historic building comply with the sf-abe program. compliance affidavits and plans were submitted in 2018 and 2019 evidencing "technical infeasibility per ordin. 51-16."abe#20190529 -5824/5825/5826/5827/5828.Details
confirmation that (e) entrances approved and finaled in 1985 in this historic building comply with the sf-abe program. compliance affidavits and plans were submitted in 2018 and 2019 evidencing "technical infeasibility per ordin. 51-16."abe#20190529 -5824/5825/5826/5827/5828. | $1,000 | |
| Dec 30, 2022 | Never finaled filed Dec 2022, never issued | 1109 Geary Bl | confirmation that (e) entrances approved and finaled in 1985 in this historic building comply with the sf-abe program. compliance affidavits and plans were submitted in 2018 and 2019 evidencing "technical infeasibility per ordin. 51-16."abe#20190529 -5824/5825/5826/5827/5828.Details
confirmation that (e) entrances approved and finaled in 1985 in this historic building comply with the sf-abe program. compliance affidavits and plans were submitted in 2018 and 2019 evidencing "technical infeasibility per ordin. 51-16."abe#20190529 -5824/5825/5826/5827/5828. | $1,000 | |
| Dec 30, 2022 | Never finaled filed Dec 2022, never issued | 1119 Geary Bl | confirmation that (e) entrances approved and finaled in 1985 in this historic building comply with the sf-abe program. compliance affidavits and plans were submitted in 2018 and 2019 evidencing "technical infeasibility per ordin. 51-16."abe#20190529 -5824/5825/5826/5827/5828.Details
confirmation that (e) entrances approved and finaled in 1985 in this historic building comply with the sf-abe program. compliance affidavits and plans were submitted in 2018 and 2019 evidencing "technical infeasibility per ordin. 51-16."abe#20190529 -5824/5825/5826/5827/5828. | $1,000 | |
| Dec 30, 2022 | Never finaled filed Dec 2022, never issued | 1111 Geary Bl | confirmation that (e) entrances approved and finaled in 1985 in this historic building comply with the sf-abe program. compliance affidavits and plans were submitted in 2018 and 2019 evidencing "technical infeasibility per ordin. 51-16."abe#20190529 -5824/5825/5826/5827/5828.Details
confirmation that (e) entrances approved and finaled in 1985 in this historic building comply with the sf-abe program. compliance affidavits and plans were submitted in 2018 and 2019 evidencing "technical infeasibility per ordin. 51-16."abe#20190529 -5824/5825/5826/5827/5828. | $1,000 | |
| Mar 11, 2022 | Never finaled filed Mar 2022, never issued | 290 San Bruno Av | two buildings on site sharing a common parking lot.one building will be demolish and will be converted into space trailer staging area for loading & unloading packages during the last weeks of the year. demo permit under bpa#202203119821. install new trash enclosure.Details
two buildings on site sharing a common parking lot.one building will be demolish and will be converted into space trailer staging area for loading & unloading packages during the last weeks of the year. demo permit under bpa#202203119821. install new trash enclosure. | $800,000 | |
| Mar 11, 2022 | Never finaled filed Mar 2022, never issued | 290 San Bruno Av | demolish (e) 2-story office building.Details
demolish (e) 2-story office building. | $160,000 |