Andres Stambuk
- Listed as
- architect, engineer
- Firm
- Cres Engineering
- On San Francisco permits
- Mar 2005 to Dec 2022
10 permits since 2000 (engineer on 7 permits, architect on 3 permits): 6 completed, 1 in progress, 3 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Dec 23, 2022 | Completed final sign-off Jun 2024 | 131 Paris St | Labor Unlimited | interior reomdel: misc repairs & improvements, minor demo of interior partitions, new interior partitions, repair of ext siding, replace exist front windows like for like, replace deck finish, bathroom remodel, replace fixtures & finishes, new dumbwaiterDetails
interior reomdel: misc repairs & improvements, minor demo of interior partitions, new interior partitions, repair of ext siding, replace exist front windows like for like, replace deck finish, bathroom remodel, replace fixtures & finishes, new dumbwaiter | $280,000 |
| Aug 22, 2020 | In progress issued Jan 2024 | 45 Bernard St | Huston General Contracting Inc. | upgrade 3-story, 4-unit apartment consisting of brick foundation, wood frame structure, combination siding, etc. project work consists of seismic/soft-story foundation upgrade (w/9 ft rear-yard addition) and includes bringing front bedroom windows to fire exit code size with finish to match existingDetails
upgrade 3-story, 4-unit apartment consisting of brick foundation, wood frame structure, combination siding, etc. project work consists of seismic/soft-story foundation upgrade (w/9 ft rear-yard addition) and includes bringing front bedroom windows to fire exit code size with finish to match existing | $389,642 |
| Mar 13, 2020 | Completed final sign-off Sep 2020 | 3625 Baker St | Integrity Construction Maintenance Inc | revision to 201910215056, 201404173549. approved plans have wood handrail, need metal handrail approved in revision. no other work to be revised.Details
revision to 201910215056, 201404173549. approved plans have wood handrail, need metal handrail approved in revision. no other work to be revised. | |
| Jan 11, 2017 | Expired or cancelled cancelled Jan 2026 | 1485 Bay Shore Bl | Huston General Contracting Inc. | adjust existing breakroom layout to incorporate adjacent storage & work rooms.Details
adjust existing breakroom layout to incorporate adjacent storage & work rooms. | $25,000 |
| Apr 6, 2015 | Completed final sign-off Mar 2016 | 233 Chestnut St | Thompson Brooks Inc. | unit #3 - interior remodel to apt. reconfigure interior walls. new elec, plugs & lighting. install n hydrovic heat system (n) kit. cabinets & appliances, (n) bath fixtures & finishes, (n) exterior wall insulation (fron interior) @ walls & attic. add w/dDetails
unit #3 - interior remodel to apt. reconfigure interior walls. new elec, plugs & lighting. install n hydrovic heat system (n) kit. cabinets & appliances, (n) bath fixtures & finishes, (n) exterior wall insulation (fron interior) @ walls & attic. add w/d | $60,000 |
| Nov 3, 2014 | Expired or cancelled withdrawn Feb 2015 | 1447 44th Av | add (n) 2-story enclosure to rear of building. add shower to 1st floor, create 3rd bedroom 1st floor.Details
add (n) 2-story enclosure to rear of building. add shower to 1st floor, create 3rd bedroom 1st floor. | $25,000 | |
| Jul 8, 2014 | Expired or cancelled cancelled Sep 2020 | 667 Waller St | Huston General Contracting Inc. | approx 9x11 room for dry sauna & reconfigure existing back deck. also replace front windows with energy efficient type.Details
approx 9x11 room for dry sauna & reconfigure existing back deck. also replace front windows with energy efficient type. | $50,000 |
| Dec 30, 2013 | Completed final sign-off Jul 2016 | 225 Clipper St | Bjlgc Inc, Huston General Contracting Inc. | foundation & concrete slab replacement, rebuild interior stair (n) fenestration & horiztal/vertical addition @ rear of bldg. upgrade to electrical & plumbing adding 1 1/2 baths. addition of single car garage, driveway & curb cut.Details
foundation & concrete slab replacement, rebuild interior stair (n) fenestration & horiztal/vertical addition @ rear of bldg. upgrade to electrical & plumbing adding 1 1/2 baths. addition of single car garage, driveway & curb cut. | $200,000 |
| Jan 17, 2012 | Completed final sign-off Feb 2012 | 2848 Sacramento St | A B S | voluntary seismic upgrade per structural drawings for 1st floor for half of 1st floor front areaDetails
voluntary seismic upgrade per structural drawings for 1st floor for half of 1st floor front area | $6,520 |
| Mar 4, 2005 | Completed final sign-off Mar 2006 | 2169 Green St | interior remodel remove and rebuild approx 15'0" of non bearing partition walls install of (n)Details
interior remodel remove and rebuild approx 15'0" of non bearing partition walls install of (n) | $50,000 |